Calculate the earliest start and finish times, the latest start and finish times and the slack days for each activity based on normal durations.

Publish By: Admin,
Last Updated: 12-Jul-23
Price: $120

Based on the data below:

(a) Draw a network diagram for the project, highlight the "normal" critical path

(b) Calculate the earliest start and finish times, the latest start and finish times and the slack days for each activity based on normal durations

(c) If indirect costs of 375 per day could be saved by reducing the overall duration of the project, what is the minimum cost for the project?

(d) What practical factors should be considered before an activity is crashed?

(e) Describe a practical approach to monitoring the progress of a project like this one.